Road A11 Liepaja–Rucava (27–50 km)

71 000 m2 | filled 42 000 m3 | removed 40 000 m3

In 2015 “CTB” Ltd. commenced extensive reconstruction on one of the most loaded state roads A11 in Kurzeme. In addition to provoking volume of construction works, the deadline of the works is relatively short, thus large civil engineering resources – up to 50 units of machinery and transport mechanisms are used.

Volume of construction works in 2015-2016
192 m – construction of the culverts
48 590 m3 – earth surface entrenchment construction
75 800 m2 – geotextile laying
109 000 m2 – asphalt recycling works
92 00 m2 – asphalt concrete surface laying
8000 m2 – road surface marking with thermoplastic

Volume of construction works 2017-2018
71 000 m2 – asphalt concrete surface laying
66 000 m2 – asphalt concrete recycling
100 000 tons – aggregate layer construction
40 000 m3 – soil removal
42 000 m3 – embankment construction works
108 000 m2 – slope fixation with soil